CO · CO_0280_2324-Q2 · Last reported March 2024
Department page: Cabinet Office
| Data as at | Rating | End date | Whole-life cost |
|---|---|---|---|
| March 2024 | Green (the department's own assessment) | 1 October 2026 | £2,335m (price basis not stated) |
Each year’s cost is shown with its price basis. Costs are not compared between years: the March 2024 and March 2025 reports state no price basis, and from March 2026 costs are in 2024/25 prices.
This is the department’s own commentary. It may use different prices from the table above, so its figures may not match.
Rating: The Senior Responsible Owner's Delivery Confidence Assessment rating at 23/24-Q4 is Green. This is primarily due to the following factors. LF2.0 completed GMPP Gate 0 review in October 2023 with an amber/green rating. We have addressed the 13 recommendations and presented this as an annexe in OBC
Schedule: The project's end-date at 23/24-Q4 is 2026-10-01. This is primarily due to the following factors. Learning Frameworks 2.0 is currently on track to deliver replacement centralised training services when current arrangements end in October 2025 . The project is still due to formally close in Jan 2026
Cost: The project's departmental-agree Whole Life Cost at 23/24-Q4 is 2335m. This is primarily due to the following factors. 17,608,147 to implement the project and to manage the contracts once they are in place (FY22-34); and _x000D_ an estimated 2,316,937,056 which is based on projections from current spend (met by the Civil Service organisations buying the training - FY 2025-34) _x000D_ Total cost: 2,334,545,203 (FY22-34)
Source: IPA Annual Report 2023-24 (data)