Manchester Digital Campus

CO · CO_0438_2425-Q3

Department page: Cabinet Office

Data as atRatingEnd dateWhole-life cost
March 2025Amber (NISTA's independent assessment)27 December 2030£1,443.7m (price basis not stated)
March 2026Amber (NISTA's independent assessment)17 December 2032£1,029.78m (in 2024/25 prices)

Each year’s cost is shown with its price basis. Costs are not compared between years: the March 2024 and March 2025 reports state no price basis, and from March 2026 costs are in 2024/25 prices.

The department’s commentary

This is the department’s own commentary. It may use different prices from the table above, so its figures may not match.

March 2026

Rating: Exempt under Section 24 - National security

Schedule: Exempt under Section 24 - National security

Cost: Exempt under Section 24 - National security

Source: NISTA Major Projects Annual Report 2025-26 (data)

March 2025

Rating: Section 24 - National security

Schedule: The project's end-date at 24/25-Q4 is scheduled to be 27/12/2030. This is primarily due to the following factors‚ Project delivery remains Dec 30.

Cost: Section 24 - National security

Source: NISTA Annual Report 2024-25 (data)

Names, figures, dates, ratings and commentary are as the department reported them. Where a rating, cost or date is withheld, the file’s wording is shown. Every major project →