Accelerated Houseblocks

MOJ · MOJ_0053_2021-Q4

Department page: Ministry of Justice

Data as atRatingEnd dateWhole-life cost
March 2024Amber (NISTA's independent assessment)Exempt under Section 22 of the Freedom of Information Act 2000 (Information intended for future publication)Exempt under Section 43 of the Freedom of Information Act 2000 (Commercial Interests) - Commercial interests.
March 2025Amber (NISTA's independent assessment)10 July 2028Section 43 - Commercial interests
March 2026Amber (NISTA's independent assessment)1 November 2030Exempt under Section 43 - Commercial interests

Each year’s cost is shown with its price basis. Costs are not compared between years: the March 2024 and March 2025 reports state no price basis, and from March 2026 costs are in 2024/25 prices.

The department’s commentary

This is the department’s own commentary. It may use different prices from the table above, so its figures may not match.

March 2026

Rating: Compared to financial year 24/25-Q4, the NISTA Delivery Confidence Assessment remains at Amber. This is primarily due to inflation and increasing cost maturity resulting in increasing cost estimates and other market risks.

Schedule: Compared to financial year 24/25-Q4 the programme’s end date changed from 10/07/28 to 01/11/30. This is primarily due to scope increases within the project resulting in more time required to achieve overall programme completion.

Cost: Exempt under Section 43 - Commercial interests

Source: NISTA Major Projects Annual Report 2025-26 (data)

March 2025

Rating: Compared to financial year 23/24-Q4, the Infrastructure Project Authority's Delivery Confidence Assessment rating at 24/25-Q4 remained at AMBER. This is primarily due to the following factors‚ Inflation, market risks, and increasing cost maturity contributing to increasing cost estimates.

Schedule: The project's end-date at 24/25-Q4 is scheduled to be 10/07/2028. This is primarily due to the following factors‚ Challenging site conditions.

Cost: Section 43 - Commercial interests

Source: NISTA Annual Report 2024-25 (data)

March 2024

Rating: Compared to financial year 22/23-Q4, the Infrastructure Project Authority's Delivery Confidence Assessment rating at 23/24-Q4 remained at Amber. This is primarily due to the following factors. Inflation risks contributing to the increasing cost estimate, which is greater than that estimated previously.

Schedule: Exempt under Section 22 of the Freedom of Information Act 2000 (Information intended for future publication)

Cost: Exempt under Section 43 of the Freedom of Information Act 2000 (Commercial Interests) - Commercial interests.

Source: IPA Annual Report 2023-24 (data)

Names, figures, dates, ratings and commentary are as the department reported them. Where a rating, cost or date is withheld, the file’s wording is shown. Every major project →